Mdot Form 1130, 2015 - Progress Schedule

Download a blank fillable Mdot Form 1130, 2015 - Progress Schedule in PDF format just by clicking the "DOWNLOAD PDF" button.

Open the file in any PDF-viewing software. Adobe Reader or any alternative for Windows or MacOS are required to access and complete fillable content.

Complete Mdot Form 1130, 2015 - Progress Schedule with your personal data - all interactive fields are highlighted in places where you should type, access drop-down lists or select multiple-choice options.

Some fillable PDF-files have the option of saving the completed form that contains your own data for later use or sending it out straight away.

ADVERTISEMENT

Michigan Department
PROGRESS SCHEDULE
Clear Form
Of Transportation
1130 (03/15)
nformation required by MDOT in order to establish a construction schedule.
I
Distribution: Original - Finance/Contracts, copy - Region, copy - Project files
FILE 102
CONTROL SECTION
JOB NUMBER
INITIAL
UPDATE
PROPOSAL ITEM NUMBER
LETTING DATE
OUTLINE OF PROPOSED ORDER OF WORK FOR CONTROLLING WORK ITEMS - when approved, this outline will become part of the contract.
DURATION OF CONTROLLING OPERATION
CONTROLLING WORK ITEM
ATTACHMENT
CRITICAL PATH
CALENDAR DAY
WORK DAY
CALENDAR DATE
START
COMPLETE
(Date/Work Day)
(Date/Work Day)
BAR CHART
LINEAR SCHEDULE
WEBBERVILLE CONSOLIDATED DRAIN MAINTENANCE & IMPROVEMENTS
CONTRACT NO. 3:
MOVE EQUIPMENT IN
3/06/17
3/09/17
CLEARING OF TREES (ALL TREES CUT DOWN)
3/10/17
3/31/17
CLEAN DITCH
5/15/17
6/16/17
PUT ROAD CROSSING IN ON ELM STREET
6/17/17
7/17/17
DIG RETENTION POND
6/05/17
7/28/17
PUT PIPING IN FROM TRACK TO RETENTION POND
7/29/17
8/11/17
FINISH SEEDING, MULCHING AND CLEAN-UP
8/12/17
8/25/17
REMARKS
CONTRACT COMPLETION
Conformance with progress clause and proposal (Maintain traffic
Yes
WORKDAYS
requirements)
OPEN TO TRAFFIC DATE(S)
Overlapping dates?
Yes, If yes, attach justification.
No
WORKDAYS
If A + B bid or rental (lane/bridge/ramp), is schedule in accordance
with contract?
Yes
A + B bid?
No
Yes ,
If yes, enter date(s):
Incentive/ Disincentive?
No
Yes
Lane/Bridge/Ramp rental
No
Yes
If yes, enter maximum total incentive amount: $
CONTRACTOR NAME (PRINT)
DATE
LOCAL AGENCY
CONTRACTOR SIGNATURE
DATE
MDOT APPROVAL - CONSTRUCTION/PROJECT ENGINEER
DATE
(Signature)
Digitally signed by Jeff Mead
Jeff Mead
3/03/17
DN: cn=Jeff Mead, o=Mead Bros Excavating INC., ou, ,
c=US
Date: 2017.03.03 15:46:32 -05'00'