Michigan Department
PROGRESS SCHEDULE
Clear Form
Of Transportation
1130 (03/15)
nformation required by MDOT in order to establish a construction schedule.
I
Distribution: Original - Finance/Contracts, copy - Region, copy - Project files
FILE 102
CONTROL SECTION
JOB NUMBER
INITIAL
UPDATE
PROPOSAL ITEM NUMBER
LETTING DATE
OUTLINE OF PROPOSED ORDER OF WORK FOR CONTROLLING WORK ITEMS - when approved, this outline will become part of the contract.
DURATION OF CONTROLLING OPERATION
CONTROLLING WORK ITEM
ATTACHMENT
CRITICAL PATH
CALENDAR DAY
WORK DAY
CALENDAR DATE
START
COMPLETE
(Date/Work Day)
(Date/Work Day)
BAR CHART
LINEAR SCHEDULE
WEBBERVILLE CONSOLIDATED DRAIN MAINTENANCE & IMPROVEMENTS
CONTRACT NO. 3:
MOVE EQUIPMENT IN
3/06/17
3/09/17
CLEARING OF TREES (ALL TREES CUT DOWN)
3/10/17
3/31/17
CLEAN DITCH
5/15/17
6/16/17
PUT ROAD CROSSING IN ON ELM STREET
6/17/17
7/17/17
DIG RETENTION POND
6/05/17
7/28/17
PUT PIPING IN FROM TRACK TO RETENTION POND
7/29/17
8/11/17
FINISH SEEDING, MULCHING AND CLEAN-UP
8/12/17
8/25/17
REMARKS
CONTRACT COMPLETION
Conformance with progress clause and proposal (Maintain traffic
Yes
WORKDAYS
requirements)
OPEN TO TRAFFIC DATE(S)
Overlapping dates?
Yes, If yes, attach justification.
No
WORKDAYS
If A + B bid or rental (lane/bridge/ramp), is schedule in accordance
with contract?
Yes
A + B bid?
No
Yes ,
If yes, enter date(s):
Incentive/ Disincentive?
No
Yes
Lane/Bridge/Ramp rental
No
Yes
If yes, enter maximum total incentive amount: $
CONTRACTOR NAME (PRINT)
DATE
LOCAL AGENCY
CONTRACTOR SIGNATURE
DATE
MDOT APPROVAL - CONSTRUCTION/PROJECT ENGINEER
DATE
(Signature)
Digitally signed by Jeff Mead
Jeff Mead
3/03/17
DN: cn=Jeff Mead, o=Mead Bros Excavating INC., ou, ,
c=US
Date: 2017.03.03 15:46:32 -05'00'