Field Change Order Form - Municipality Of Anchorage Building Safety Division

ADVERTISEMENT

FIELD CHANGE ORDER FORM
Purpose:
 To fast track the approval of minor field changes to approved plans.
 To separate small changes (those that require less than 15 minutes of plan review) from a
change that requires a regular change order.
 To enable inspectors to accept and document minor field revisions without requiring formal
change orders.
 To document the engineer, architect or designer of record approval of a minor field change.
Procedure:
 The field change order form is completed and signed by the engineer, architect or designer of
record or their designee.
 The engineer, architect, designer, contractor, project manager, etc. may submit the completed
field change order form to either the project plan reviewer or to the inspector at the job site.
Please note:
1. Non-prescriptive engineered designs require calculations and consequently plan review. It
is recommended that engineered designs be submitted directly to the plan reviewer.
2. Please include contact information so that comments or approved documents can be
emailed or faxed back to the engineer, architect, designer and/or contractor.
3. When a field change order form is submitted to the inspector in the field, the inspector will:
a. Approve the field changes; or
b. Make the determination that plan review is required.
4. Inspectors can approve field changes that are appropriate solutions to field situations and
have minimal impact on the design.
5. If plan review is required, it is the contractor’s responsibility to submit the field change order
to plan review for approval. The contractor may proceed at their own risk prior to receiving
plan review approval. The inspector will inspect the field change in accordance with the
design provided by the engineer/architect/designer, and note on the inspection report that
plan review approval is required for final resolution of the field change. The correction of
any deficiencies discovered by plan review is the responsibility of the permit applicant
and/or owner.
6. Field change orders, due to their minor nature, do not involve a fee. Field changes that
require more than 15 minutes plan review time do not qualify as a field change orders.
These changes require the standard change order process and involve a fee.
7. The inspector will return the accepted field change order to the department for filing. It is
the contractor’s responsibility to obtain copies for their records.
Plan Reviewer
Email
Fax
Becky Hellman
249-7400
Leigh Bergstrom
249-7615
Don Crafts
249-7652
Wayne Bolen
249-7393
Mark Panilo
249-7679
Rodney Wehr
249-7531
David Abuobaid
249-7775
Ron Wilde
249-7418

ADVERTISEMENT

00 votes

Related Articles

Related forms

Related Categories

Parent category: Business
Go
Page of 2