Developer:
"I certify under the penalty of law that the construction of this project will be performed under my direction or supervision to assure conformance with 327
IAC 8-3.5. The construction of proposed project will meet all local rules or laws, regulations and ordinances. The information submitted is, to the best of my
knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility
of fine and imprisonment."
Signature of developer
Date signed (month, day, year)
Public Water System:
"I certify under the penalty of law that I have agreed to furnish water to the area in which the water main is proposed. I acknowledge the public water system's
responsibility for examining the plans and specifications to determine that the proposed water main meet local rules or laws and ordinances. I also acknowledge
the public water system's responsibilities as outlined in 8-3.5-12. I am aware that there are significant penalties for submitting false information, including the
possibility of fine and imprisonment."
Date signed (month, day, year)
Signature of PWS official
20. Project Design Criteria:
Alternative Technical Standards (327 IAC 8-3.2.20)
21. Are any "Alternative Technical Standards" proposed to be used in this project?
Yes, I have attached copies of the approval with the NOI.
No
Public Water System Capacity Status
MGD
22. The PWS's Daily Production Firm Capacity:
B.
GPM
A.
23. The PWS's five (5) highest demand days in the previous two (2) years:
Demand (MGD)
Date
1.
2.
3.
4.
5.
C.
MGD
24. Average of five Peak Daily Demand (PDD) listed above:
25. Ratio of PDD to PWS Daily Production Capacity = (Item D = Item C / Item A x 100)
D.
%
26. Anticipated Customer Demand of Proposed Water Main
Residential Customers:
Total Average Daily Demand times Peaking Factor (G = E x F)
F. Average Daily Demand times Peaking Factor (at least 0.87 gpm/home)
E. Number of homes
G.
gpm
Other (Commercial and Industrial) Customers:
Average Daily Demand ( the "Safe Maximum
Description (including size of domestic meter):
Operating Capacity" of domestic meter)
gpm
gpm
H.
Sub Total:
gpm
Total Customer Demand of Proposed Water Main (gpm) = (Item G + item H)
I.
gpm
27. Ratio of total Customer Demand of Proposed Water Main (gpm) to the PWS Daily Production Firm Capacity (gpm)
J.
%