Project Items Check List Template Page 4

ADVERTISEMENT

Project Started
Submit for approval contractor borrow and/or waste areas, (cross section if
Project Manager and/or
1
applicable.)
Inspector
At least one month before construction of drilled shafts insure that the
Project Manager and/or
2
contractor has submitted a drilled shaft installation plan.
Inspector
Sample soil from borrow area and submit to regional materials lab for
Project Manager and/or
3
standard proctor & atterburg limits.
Inspector
Enter all test results and pay quantities (at a minimum of weekly.)
Project Manager and/or
4
Inspector
Insure that all survey information is turned in to meet specification which
Project Manager and/or
5
should include that the section corners have been referenced
Inspector
258
Check with CMS technician /Office Coordinator to insure that notice to
Project Manager
6
proceed has been issued.
Check with CMS technician/Office Coordinator to insure that all
Project Manager
7
subcontractors for the project have been approved.
258A
Notify the CMS technician/Office Coordinator of work starting this date,
Project Manager
8
same day work begins. Notice of Work Starting
7 days in advance of the work, submit any information concerning road
Project Manager and/or
9
closures, lasting for more than one day to the Construction Office.
Inspector
Submit weekly: data transfer disk
Project Manager and/or
10
Bookkeeper
Submit daily to the Construction Office: Lane closures or traffic control
Project Manager and/or
1
changes for the next days work prior to 3:30 PM.
Inspector
Submit Bi-monthly: Data transfer disk containing template data, which has
Project Manager and/or
12
been checked against field books for contractor pay estimates.
Bookkeeper
Check contractor bulletin board to insure conformance with special
Project Manager and/or
13
provisions.
Inspector
Videotape designated haul roads that were submitted at the preconstruction
Project Manager and/or
14
conference.
Inspector
Check to insure that the contractor has submitted an information sheet
Project Manager and/or
15
(information on surveyor) to the office.
Inspector
Check certified payrolls weekly for both the Prime and sub-contractors.
Project Manager and/or
16
Inspector
Submit to Office reports for trainee hours.
Project Manager and/or
17
Bookkeeper
209
Conduct wage rate interviews, one per quarter, per contractor or sub-
Project Manager and/or
18
contractor.
Inspector
4