Given the information provided below and the Gantt chart layout provided, you are to construct a
Gantt chart, with overlaps as specified.
Activity
Duration
Overlap
Activity Description
Predecessor
Letter
(months)
(months)
A
Train project team
None
1
None
2 ½
¼
B
Project paperwork and systems design
A
C
Modify purchased package
B
2
1
1 ½
D
Manual systems flow
B
1
E
Modify in-house procedures
B
4
1
1 ½
F
Test and implement modifications to purchased package
C
1/8
¾
G
Test and implement manual
D
1/8
H
Test and implement modifications to in-house procedures
E
1
1/8