PURPOSE
1.1
To provide instructions for Materials, Quality, Receiving Inspection and the
Supplier to correctly submit and process First Article Inspection items. This
procedure is not applicable to Standard Catalog Hardware or Deliverable
Software.
2.
INSTRUCTIONS
2.1
Materials, following discussion with the supplier determines that a First Article
Inspection is required due to one or more of the following issues:
This procedure is not applicable to Standard Catalog Hardware or Deliverable
Software.
Standard Catalog Hardware: A part or material that conforms to a published
industry standard or US national authority published specification: Mil-Std,
NAS, ASTM, SAE, etc.
2.1.1 New design
2.1.2 New supplier
2.1.3 New or modified tooling
2.1.4 Change in method or process to manufacture part
2.1.5 Engineering or design change by Firstmark or Firstmark ’s
customer including a material change (change in form, fit or
function)
2.1.6 Change in location of manufacturer (Supplier has relocated)
2.1.7 Item not manufactured within the last 24 months
NOTE: If FAC Quality and Engineering determines that changes made to Design/Processes
do not affect fit, form, function or interchangeability, Quality shall complete Form 10.01.03 and
upload into electronic FAI database to document the change.
2.2 Materials communicates the requirement for First Article Inspection to the Supplier
and to Receiving Inspection by listing the First Article Inspection quality code per
Printed copies are for reference only!