Project Status Report Template

ADVERTISEMENT

USDA
Farm Service Agency
Project Status Report
[Template]
Project Name:
Date:
Project Manager:
1.0 Milestones and Schedule Dates
Estimated
Completion
Percent
Milestones
Date
Complete
2.0 Accomplishments This Period
2.1
Activities
[Describe the major activities accomplished this period.]
2.2
Activities Planned But Not Achieved
[Describe the major activities planned but not yet accomplished.]
2.3
Deliverables Completed
[Describe the deliverables and/or milestones accomplished this period.]
2.4
Deliverables Planned But Not Completed
[Describe the deliverables and/or milestones planned but not yet accomplished.]
3.0 Accomplishments Planned for Next Period
3.1
Activities
[Describe the major activities that will be accomplished for the next period.]
3.2
Deliverables
[Describe the deliverables and/or milestones that will be accomplished for the next period.]
4.0 To Date Earned Values
PV
AC
EV
CV
SV
CPI
SPI
EAC
Current
* Earned Value Indicators:
• PV = Planned Value or Budgeted Cost of
• CV = Cost Variance
• SPI = Schedule Performance Index
• SV = Schedule Variance
• EAC = Estimate at Completion
Work Scheduled
• AC = Actual Cost of Work Performed
• CPI = Cost Performance Index
• EV = Earned Value or Budgeted Cost of
Work Performed,
[Add any comments here.]