D-4181-Uc, 2014, Utility Relocation Clearance Report Instructions

ADVERTISEMENT

Appendix A
Publication 16 (DM-5)
Figure A-1100
Page 1 of 3
(09/14)
D-4181-UC (9-14)
UTILITY RELOCATION
CLEARANCE REPORT
INSTRUCTIONS
State Route – Identify the state route for the proposed facilities.
Station to Station or Segment & Offset to Segment & Offset – Identify the location of the
proposed facilities.
RT/LT – Identify if the proposed facilities are right or left of the highway centerline.
Brief Description of the Adjustment – Identify the type of work required for the
relocation/adjustment (i.e., install new pole, relocate gas line, etc.).
Type of Relocation - Each Location – Identify the type of relocation for each location. See the
definitions for the different types of relocations on the form.
Describe Conditional Restrictions or Time Requirements for Coordinated Work – Identify any
conditional restrictions or time requirements for the utility work, including sequencing of utility
work. See the definitions for the different types of relocations on the form.
Calendar Days Required or Date of Completion – Identify how many calendar days are required
to complete the work for each location. For PRIOR work, give the anticipated or actual
completion date.
o If applicable, the utilities should also include time to order material, the sequencing of
operations between utilities and scheduling crews and outages.
Sign and Date the form.
If needed, attach additional sheets to list additional information.