Example1: Computer assembly (III)
Let us assume that we have three orders (computers
to manufacture).
According to the nature of each order (components, type,
etc.), we can have some estimate of the average times
(minutes) for each step:
Motherboard
Devices
Test
Order #1
2
15
7
Order #2
3
10
5
Order #3
2
12
5
The objective of the company is to keep the average
time to assembly a computer as lowest as possible
10