RENOVATION TO HAMMOND BUILDING
PSU PROJECT NO. 02-66666
MATERIAL COSTS
ITEM
QUANTITY
UNIT COST
TOTAL COST
2/0 Bare CU. Wire
79 Ft
$2.22
$175.38
3/4" X 10'0" Ground Rod
4 Ea
$38.50
$154.00
Cad-Weld 2/0 to 3/4" Rod w/#115 Charge
4 Ea
$6.44
$25.76
Cad-Weld 2/0 Tee w/#90 Charge
1 Ea
$6.44
$6.44
Excavation and Backfill
33 CY
$29.70
$980.10
Crushed Stone #2B Incl. Placement @ Vault
1 Ton
$15.08
$15.08
Pre-cast Transformer Vault 7'X7'X4'
1 Ea
$3,450.00
$3,450.00
Transformer ***
1 Ea
$5,000.00
$5,000.00
Sub-Total
$9,806.76
Material Markup (10%)
$980.68
Applicable Sales Tax
$588.41
MATERIAL TOTAL
$11,375.85