Example
Basis of Estimates Form
Assumptions: :
[Enter any constraints here.]
[Example:
1. There is rack space, power and Network connectivity in the Data Center.
2. That there are two IPs in available for use and that will be assigned to the Firewall.
3. That the Network Technician and Firewall engineer have access to the data center
during normal working hours for the contractor.
4. That the Software and Hardware Engineers or their representatives will meet in a
timely manner to discuss the rule set.
5. That the Firewall Hardware and licenses are available in accordance with the
schedule.]
Resources:
[Enter the “who” here. This is who will do the work + whatever else is
needed]
[Example:
–Labor by Activity:
• 1 Network Technician to rack the device, connect power and network cables. = 1 hour
• 1 Firewall engineer to install the standard firewall rule set and set up the base
configuration. = .25 hours (15 minutes)
• 1 Firewall engineer to optimize the firewall rule set based on meetings with the S/W
and H/W engineers = 2 hours.
• 1 Firewall engineer to Test the optimized the firewall rule set = 30 minutes.
• 1 Software engineer to Test the optimized the firewall rule set = 30 minutes.
–Hardware Bill of Material:
• 1 ea. Nokia 660 Firewall with RAM kit,
• 2 ea. patch cables
• 1 ea. Power cord
• 1 ea. Rack kit
• 1 ea. Checkpoint License with 25 IP addresses.
-Engineering Travel
The Firewall engineer will travel from the Contractors Facility in Annapolis MD to the Clients
Facility in Odenton, MD and back for meeting with the Clients H/W and S/W staff and will
configure the final Firewall Policy at that time = 30 minutes Drive Time + 22 Miles each way]
Attachment 3