Building Contract Memorandum Of Agreement And Conditions Of Contract Page 2

ADVERTISEMENT

Page 2.
1.6
"SERVICES" shall mean water and electricity supply, sewerage and
roads to the boundary of the PROPERTY.
2.
INTRODUCTION
2.1
The BUILDER has agreed to construct a home for the OWNER on the
PROPERTY for the CONTRACT SUM.
2.2
The CONTRACT SUM shall (if applicable) be secured in terms of the
mortgage bond referred to in the agreement of sale.
2.3
The CONTRACT SUM shall not be subject to increase unless
commencement of the home is delayed by the OWNER beyond six (6)
months after the date of signature hereof; (In the event of such delay, the
contract sum shall be increased by the amount equivalent to the
consumer price index change from the date of signature hereof to the
date of commencement of the building.)
3.
AGREEMENT
3.1
The BUILDER and the OWNER agree that the construction of the home
shall be undertaken and completed by the BUILDER within a period of 12
months from the date hereof.
3.2
The construction shall be carried out in accordance with this agreement
which shall include:
3.2.1 the general building and design requirements set out in Annexure
"C";
3.2.2 the building plans as set out in Annexure "F";
3.2.3 the specifications as set out in Annexure "G".
4.
PAYMENT
4.1
The CONTRACT SUM:
4.1.1 shall be secured in terms of the mortgage bond referred to in the
agreement of sale or a bank guarantee, or cash paid into trust to the
BUILDER'S attorney, or any other security acceptable to the
BUILDER prior to commencement of the construction of the home;