18.2 Refusing to proceed with the building with reasonable diligence; or
18.3 Refusing, after notice in writing from the OWNER, to remove defective
work or improper materials;
then, if such default shall continue for FOURTEEN (14) days after a registered
letter has been sent to the BUILDER from the OWNER specifying same, the
OWNER may, without prejudice to any other rights he may have in terms of this
contract or in law, by registered post terminate the employment of the BUILDER
under this contract, provided no dispute has been declared in terms of Clause
17. In such event the BUILDER shall be liable for all damages incurred by the
OWNER by reason of such default.
19. OWNER'S DEFAULT
19.1 Should the OWNER commit a breach of any of the terms of this contract,
all of which terms shall be material, and not rectify such breach after
having been given SEVEN (7) days notice by registered post to do so,
the BUILDER shall be entitled forthwith to give the OWNER, per
registered post, written notice of the termination of this contract, without
prejudice to any other rights which the BUILDER may have in terms of
this contract or in law.
19.2 Failure by the OWNER to make any payment due shall entitle the
BUILDER, on giving SEVEN (7) days' written notice to the OWNER, to
cease work under this contract until payment shall have been made to
the BUILDER.
The time during which such works shall cease shall
operate as an automatic extension of time for completion and occupation,
unless the contract specifies to the contrary in writing
19.3 A certificate signed by an engineer or a registered quantity surveyor
specifying the amount due by the OWNER to the BUILDER shall be
sufficient proof of any amount due to the BUILDER in terms of the
contract, and may also be used by the BUILDER for the purposes of
obtaining judgement by provisional sentence against the OWNER in any
court of law having jurisdiction in respect thereof. Where the OWNER is
in default the cost of obtaining the engineer's or quantity surveyor's
certificate shall be for the OWNER'S account.
20. PC ITEMS
The purchaser acknowledges that a delay in choosing the PC items reflected in
the Building Plans and Specifications could prejudice the seller and accordingly:
20.1 the purchaser shall be obliged to choose the PC items within one (1)
week of being requested to do so;
20.2 in the event that the purchaser fails to choose the PC items, he hereby
irrevocably authorises the seller to do so on his behalf.