TWO WEEK LOOK AHEAD CONSTRUCTION SCHEDULE
PROJECT:
LOM 437 Interior Build Out
PERIOD:
07/15/13
-
07/28/13
SUPERINTENDENT:
PROJECT MANAGER:
TRINIDAD CONSTRUCTION, LLC.
Current Week
9700 South Cass Avenue
Randy King
Jonathan Gasior
LOCATION:
Trinidad Construction
Trinidad Construction
Lemont, IL 60439
(708) 473-9125 Cell
(773) 617-4481 Cell
M
T W T
F
S
S
M T W T
F
S S M
T
W T
F
S S
DESCRIPTION OF WORK
SUBCONTRACTOR
Commets
08 09 10 11 12 13 14
15 16 17 18 19 20 21 22 23 24 25 26 27 28
Frame hallway walls in pentagons A, B, D & E
Trinidad
Complete
Sawcut floors for floor boxes
Litgen
Complete
Rough in electrical for floor boxes
West Elsdon
Complete
Fill in floor trench
Trinidad
Complete
Relocated sprinkler line for mechanical rough in Pentagons A & B
Hill/Ahern
x
Install duct work in pentagons D & E
McCauley
x
x
x
x
x
Install piping in pentagons D & E
McCauley
x
x
x
x
x
Mecanical Piping in penthouse
McCauley
x
x
x
x
x
x
x
x
x
x
x
x
x
x
Above ceiling electrical in Pentagons D & E
x
x
x
x
x
West Elsdon
x
x
x
x
x
Frame walls under windows
x
x
x
Trinidad
Drywall inside wall of hallways Pentagons A, B, D & E
x
x
Trinidad
Install Ceiling Grid Pentagons D & E
D&M
x
x
Install Duct work in pentagons A & B
McCauley
x
x
x
x
x
x
x
Install piping in pentagons A & B
McCauley
x
x
x
x
x
x
x
Above ceiling electrical in pentagons A & B
West Elsdon
x
x
x
x
x
x
x
Frame office walls pentagons D&E
Trinidad
x
x
x
x
x
Install ceiling grid pentagons A & B
D&M
x
x
Frame office walls pentagons A & B
Trinidad
x
x
x
x
x
Rough wall electrical in Pentagons D&E
West Elsdon
x
x
x
x
Rough wall electrical in Pentagons A&B
West Elsdon
x
x
x
x
Install insulation in Pentagons D&E
Trinidad
x
x
x