Comments
Any time you report Red
or
Yellow status, in the above seven status fields you must state why the status is at risk in
the Comments section. Consider including the following:
List any current major issues
List any major risks (with mitigation strategy if known)
Always review your comments area and delete those comments that do not apply to the current reporting
period.
Date Status Updated
Change this date each reporting time period the information is updated.
This date verifies that the information given in this report has been updated by the project manager in the
current reporting period.
Monthly Reporting – Review and update fields as needed
Although information in other PPM fields may change, the following fields typically need to be updated throughout the
lifecycle of every project:
Total Cost Planned
Approved Finish Date
Project Phase
Project State