Project Management Plans Page 2

ADVERTISEMENT

It includes an overview or summary of project scope, cost, and schedule. The suggested project plan outline
includes the following subjects:
1.
Introduction. Describes the purpose and overview of the plan. It outlines, in summary form, the strategy
of the project plan versus details in the supporting appendixes that follow.
2.
Project Objectives. Describes the purpose of the deactivation project and explains its driving objectives,
which are covered in Section 3.1 of this Guide.
3.
Project Scope. Describes the facilities (addressed in Section 4.2.1 of this Guide) that will be deactivated
and the major actions which comprise the project.
4.
Project Organization. Describes the project organization and all functional relationships and discusses the
roles and responsibilities with respect to accomplishing the project objectives.
5.
Project Management and Control. Describes the systems and processes to be used to manage and control
all aspects of the project (e.g., cost, schedule, scope). This section of the project plan document also
includes a process for issue resolution and technical decision making.
6.
Project Baseline. Contains a roll-up summary of the work breakdown structure, schedule, proposed
milestones, and cost estimate. These subjects are addressed in more detail in Section 4.2.5 of this Guide.
7.
End Points. Describes the process used to develop the end points. Section 4.2.3 of this Guide addresses
the development of end points for a deactivation project.
8.
Quality Assurance. Describes the policies and procedures to be used to meet quality assurance objectives.
9.
Regulatory. Provides an overview of the deactivation project regulatory drivers and the proposed
approaches to ensuring compliance.
10. Safety and Health. Provides the safety basis and the strategy and methods to be used for evaluating the
hazards associated with the project activities. The strategy includes integration of worker safety and
health issues as well as protection of the public and dislocated site workers. Incorporating safety into the
deactivation project is addressed in detail in Section 4.2.2 of this Guide as well as in DOE-STD-1120-98,
Section 3.0, "Integrated Safety Management System."
11. Communications. Outlines a plan for public and stakeholder outreach and involvement and provides the
proposed communications objectives and methods. Section 4.2.4 of this Guide discusses the need for
open communications during the deactivation project.
12. Project Risk. Provides an outline of the method to be used in performing a project risk assessment.
The supporting appendixes to the deactivation project plan provide the detailed documentation for application and
implementation of the project strategies. The supporting appendixes also provide the detailed cost and schedule
data. These appendixes are used to provide guidance to project staff for day-to-day management of the project
and are developed, maintained, and approved by the deactivation contractor. The following topics and their
descriptions are suggested as supporting appendixes to be included as part of the project plan.
Work Management
Current Fiscal Year Execution Plan
Schedules
Work Breakdown Structure Dictionary and Basis of Estimate
Cost Estimate Work Sheets
Schedule Preparation and Change Control
Configuration Control
Project Metrics
End-Point Document
End-point Closure Methods and Practices
S&M Plan
Health and Safety Documentation
Project Risk Assessment
Radiological Controls
Waste Management
Closure Plan
During development of the deactivation project plan, facility conditions and/or business situations are identified
that necessitate the inclusion of more than the usual plan elements. The deactivation project plan should include
additional appendixes, other than those previously suggested, which address the following on an as-needed basis
and as agreed upon by management:
Separate identification of costs to operate and maintain the facility, exclusive of direct deactivation tasks
Resource needs for the deactivation of existing facilities
Technical integration with other projects and activities

ADVERTISEMENT

00 votes

Related Articles

Related forms

Related Categories

Parent category: Business
Go
Page of 4