MBC Part 6:
3.1
HVAC systems and devices, including high building requirements where applicable
3.2
Fire dampers at required fire separations
3.3
Continuity of fire separations at HVAC penetrations
3.4
Functional testing of mechanical related fire emergency systems and devices
3.5
Maintenance manuals for mechanical systems
3.6
Structural capacity of mechanical components
3.7
Review of applicable shop drawings
3.8
Geothermal loops
3.9
MECB – Part 5: HVAC Systems
MPC Part 7 :
4.1
Roof drainage systems
4.2
Site and foundation drainage systems
4.3
Plumbing systems and devices
4.4
Continuity of fire separations at plumbing penetrations
4.5
Functional testing of plumbing related fire emergency systems and devices
4.6
Maintenance manuals for plumbing systems
4.7
Structural capacity of plumbing components
4.8
Review of all applicable drawings
4.9
MECB – Part 6: Service Water Heating Systems
FIRE SUPPRESSION SYSTEMS
5.1
Suppression system classification for type of occupancy
5.2
Design coverage, including concealed or special areas
5.3
Compatibility & location of electrical supervision, ancillary alarm controls
5.4
Evaluation of the capacity of city (municipal) water supply versus systems demands &
domestic demand, including pumping devices where applicable
5.5
Qualification of welder, quality of welds and material
5.6
Review of all applicable drawings
5.7
Acceptance testing for "Contractor's Material and Test Certificate" as per NFPA Standards
5.8
Maintenance program and manual for suppression systems
5.9
Structural capacity of sprinkler components
5.10 For partial systems - confirm sprinklers are installed in all areas
5.11 Fire Department connections and hydrant locations
5.12 Fire hose standpipes
5.13 Functional testing of fire suppression systems and devices
ELECTRICAL
6.1
Electrical systems and devices, including high building requirements where applicable
6.2
Continuity of fire separations at electrical penetrations
6.3
Functional testing of electrical related emergency systems and devices
6.4
Electrical systems and devices maintenance manuals
6.5
Structural capacity of electrical components
6.6
Clearance from buildings of all electrical utility equipment
6.7
Fire Protection of wiring fire emergency systems
6.8
Review of all applicable drawings
6.9
MECB – Part 4: Lighting
6.10 MECB – Part 7: Electrical Power Systems and Motors
GEOTECHNICAL ------- Temporary
7.1
Excavation
7.2
Shoring
7.3
Underpinning
7.4
Temporary construction