Critical-Path Analysis For Network Scheduling Page 5

ADVERTISEMENT

Back to Our Case Study Project
We need to do the following:
Calculate ES, LF, & TF for all activities. Identify critical ones. Draw a Late Bar Chart for the project.
-
What is the effect of delaying activity H by two days on project duration?
-
Solution:
Activity
Duration
ES
LF
TF=LF-ES-d
Critical
A
4
B
6
C
2
D
8
E
4
F
10
G
16
H
8
I
6
J
6
K
10
ACTIVITY
1
2
3
4
5
6
7
8
9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
31 32
A
B
C
D
E
F
G
H
I
J
K