Introduction
This Guidance Note gives practical information about hot work permits
Alternatives to hot work (i.e. cold cutting) should be undertaken whenever reasonably practicable where there is a risk of fire or
explosion. Where hot work is unavoidable, it should not be carried out unless it is authorised and properly supervised by an experienced
manager or supervisor who has knowledge of the work to be carried out, the risks involved and the precautions to be taken.
What is a hot work permit?
A permit-to-work system is a formal written system and is an extension of the safe system of work. A hot work permit is used to prevent
fire or explosion and will specifically detail the work to be carried out, how and when it is to be done and the precautions to be taken.
The use of a permit system does not, by itself, make the job safe. It supports the safe system, providing a ready means of
recording findings and authorisations required to undertake hot work.
The hot work permit should check the following items (where appropriate):
Preparation of work area, including isolation, emptying, cleaning, gas-freeing, inerting, etc.
Good housekeeping
Use of protective curtains
All 'hot works' equipment should be regularly maintained and inspected
Ensure a competent person visits the area after the hot works has finished to ensure that no
smouldering embers or hot surfaces remain
Provision of suitable fire extinguishers
Ensure that sprinklers (if installed) are isolated and reactivated after the works
On satisfactory completion of the job, the authorising person should cancel the permit.
Re-issue of the permit
If the work has not been completed before the permit expires, a re-issue of the permit is
required. The responsible person must visit the location and ensure that conditions have not
substantially altered since the certificate was initially issued. If the conditions have altered
the situation must be reassessed and, as necessary, further controls should be specified.
End of operations
On completion of hot work, the permit must be signed-off and returned to the permit issuer,
stating that the work area is safe for normal operations and that all workers are clear from
the work area. The process operator should check the essential services and if agreed, the
permit should be cancelled.
Operation review and revision
Following each operation the procedures will be reviewed and revised, as necessary.
Periodically, persons in charge should review the permit-to-work system to ensure that
permits are being correctly completed, and that the required controls are being adopted.