Rating Guidelines
Quality of Product or Service; Timeliness of Performance; and Business Relations
0 = Unsatisfactory 1 = Marginal 2 = Satisfactory 3 = Very Good 4 = Exceptional
Unsatisfactory
Performance does not meet most contractual requirements and recovery is not likely in a timely manner.
The contractual performance of the element or sub-element contains a serious problem(s) for which the
contractor’s corrective actions appear or were ineffective.
NOTE: To justify an Unsatisfactory rating, identify multiple significant events in each category that the
contractor had trouble overcoming and state how it impacted the Government. A singular problem,
however, could be of such serious magnitude that it alone constitutes an unsatisfactory rating. An
Unsatisfactory rating should be supported by referencing the management tools used to notify the
contractor of the contractual deficiencies (e.g., management, quality, safety, or environmental deficiency
reports, or letters).
Marginal
Performance does not meet some contractual requirements. The contractual performance of the element
or sub-element being assessed reflects a serious problem for which the contractor has not yet identified
corrective actions. The contractor’s proposed actions appear only marginally effective or were not fully
implemented.
NOTE: To justify Marginal performance, identify a significant event in each category that the contractor
had trouble overcoming and state how it impacted the Government. A Marginal rating should be
supported by referencing the management tool that notified the contractor of the contractual deficiency
(e.g., management, quality, safety, or environmental deficiency reports, or letters).
Satisfactory
Performance meets contractual requirements. The contractual performance of the element or sub-element
contains some minor problems for which corrective actions taken by the contractor appear or were
satisfactory.
NOTE: To justify a Satisfactory rating, there should have been only minor problems, or major problems
the contractor recovered from without impact to the contract. There should have been NO significant
weaknesses identified. A fundamental principle of assigning ratings is that contractors will not be assessed a
rating lower than Satisfactory solely for not performing beyond the requirements of the contract.
Very Good
Performance meets contractual requirements and exceeds some to the Government’s benefit. The
contractual performance of the element or sub-element being assessed was accomplished with some minor
problems for which corrective actions taken by the contractor was effective.
NOTE: To justify a Very Good rating, identify a significant event and state how it was a benefit to the
Government. There should have been no significant weaknesses identified.
Performance meets contractual requirements and exceeds many to the Government’s benefit. The
Exceptional
contractual performance of the element or sub-element being assessed was accomplished with few minor
problems for which corrective actions taken by the contractor was highly effective.
NOTE: To justify an Exceptional rating, identify multiple significant events and state how they were of
benefit to the Government. A singular benefit, however, could be of such magnitude that it alone
constitutes an Exceptional rating. Also, there should have been NO significant weaknesses identified.