DAILY OBSERVATION REPORT
Job No.:
415-2328-007
Phase:
003C
Task:
RQ01
Report No.
8
Terminal 4 Wheeler Bay Shore Line Restoration
Project:
Owner:
Port of Portland
Page
1
1
of
Contractor:
Northwest Earthmovers Inc.
Date:
October 14, 2010
Jeff Hargens, Project Manager
Day:
Thursday
Contractor’s Rep./Title:
48
67
Foggy, Sunny, Dry,
Weather A.M.:
° F
P.M.:
° F
Site Conditions: (Good) (Fair) (Poor)
Location and Type of Work:
T4 Wheeler Bay Shore Line Restoration
Number and Classification of Contractors, Men, and Equipment (include condition of equipment):
Carl Johnson, NEI
1-Hitachi 160 track hoe
1-NEI work truck
Mike Madison, NEI
1-CAT IT28G front loader
1-end dump
Tim Stone, Anchor, Port Inspector
4-steel sheets
Work in Progress (include report of operations, materials received and condition, work start/stop time, and any unusual conditions):
Tried installing the first large woody debris anchors but the method that NEI was using did not work. NEI will have a new method of
installation tomorrow.
Work Completed:
Two loads of large woody debris were delivered to the site for a total of 8 logs.
9 rolls of Coir Fabric were delivered to the site.
Exchanged the Hitachi 160 track hoe out the sample model Hitachi 160 track hoe. The new track how can be fitted with the hoe
compaction plate. The compaction plate is how the anchors will be driven into the ground.
Discussions with Contractor (include orders given and received):
Any Cause for Dispute, Change Orders, or Delays, and Reasons:
Extra Work in Progress–Description (include Extra Work Report Form):
Items for Office Action:
Visitors:
Notes:
NEI will be working tomorrow. They plan on delivering more large woody debris and installing anchors.
Ingmar Saul, R.G.
Signature
Port of Portland Terminal 4 Phase I Removal Action, Oversight by U.S. EPA