DAILY OBSERVATION REPORT
Job No.:
415-2328-007
Phase:
003C
Task:
RQ01
Report No.
9
Terminal 4 Wheeler Bay Shore Line Restoration
Project:
Owner:
Port of Portland
Page
1
1
of
Contractor:
Northwest Earthmovers Inc.
Date:
October 15, 2010
Jeff Hargens, Project Manager
Day:
Friday
Contractor’s Rep./Title:
Foggy, Sunny, Wet,
48
65
Slight Breeze
Weather A.M.:
° F
P.M.:
° F
Site Conditions: (Good) (Fair) (Poor)
Location and Type of Work:
T4 Wheeler Bay Shore Line Restoration
Number and Classification of Contractors, Men, and Equipment (include condition of equipment):
Carl Johnson, NEI
1-Hitachi 160 track hoe
1-NEI work truck
Mike Madison, NEI
1-CAT IT28G front loader
1-end dump
Tim Stone, Anchor, Port Inspector
4-steel sheets
Work in Progress (include report of operations, materials received and condition, work start/stop time, and any unusual conditions):
The solid steal 2 inch rod that was used to drive the anchors into the ground was not strong enough to keep from bending and only
one anchor was driven before the rod bent. What NEI will do know is drive a pilot hole first before driving the anchor into the
ground. NEI fabricated a 3 inch pilot hole rod at the site. After driving the first pilot hole the weld holding the pilot hole rod broke on
the hoe pack and no more anchors could be set. NEI will redesign the welds on the hoe pack over the weekend and be ready to go
on Monday.
Work Completed:
2 loads of large woody debris were delivered to the site for a total of 11 logs. The total number of logs delivered to the site is 29.
Discussions with Contractor (include orders given and received):
Any Cause for Dispute, Change Orders, or Delays, and Reasons:
Extra Work in Progress–Description (include Extra Work Report Form):
Items for Office Action:
Visitors:
Jeff Hargens, NEI;
Notes:
Rained last night.
Work will start at 0730 on Monday since it is still dark at 0700.
Ingmar Saul, R.G.
Signature
Port of Portland Terminal 4 Phase I Removal Action, Oversight by U.S. EPA