Daily Observation Report Page 23

ADVERTISEMENT

DAILY OBSERVATION REPORT
Job No.:
415-2328-007
Phase:
003C
Task:
RQ01
Report No.
11
Terminal 4 Wheeler Bay Shore Line Restoration
Project:
Owner:
Port of Portland
Page
1
1
of
Contractor:
Northwest Earthmovers Inc.
Date:
October 19, 2010
Jeff Hargens, Project Manager
Day:
Tuesday
Contractor’s Rep./Title:
53
70
Sunny, Dry,
Weather A.M.:
° F
P.M.:
° F
Site Conditions: (Good) (Fair) (Poor)
Location and Type of Work:
T4 Wheeler Bay Shore Line Restoration
Number and Classification of Contractors, Men, and Equipment (include condition of equipment):
Carl Johnson, NEI
1-Hitachi 160 track hoe
1-NEI work truck
Mike Madison, NEI
1-CAT IT28G front loader
Tim Stone, Anchor, Port Inspector
4-steel sheets
Work in Progress (include report of operations, materials received and condition, work start/stop time, and any unusual conditions):
Laying coir fabric, staking, and stapling in place from approximately 0-10 to 2+25.
Work Completed:
Completed placement and anchoring of large woody debris from approximately 3+60 to 7+00.
Discussions with Contractor (include orders given and received):
Any Cause for Dispute, Change Orders, or Delays, and Reasons:
Extra Work in Progress–Description (include Extra Work Report Form):
Items for Office Action:
Visitors:
Rodger Anderson, POP; Jeff Hargens, NEI; Sheila McConnell, PMX;
Notes:
Sheila McConnell, CIH, made a surprise site visit to check the health and safety procedures of the contractor.
The contractor will not be working at the site tomorrow. Contractor is waiting for the approval of the top soil before heading back out
to the site.
Ingmar Saul, R.G.
Signature
Port of Portland Terminal 4 Phase I Removal Action, Oversight by U.S. EPA