ITMA XII - Project
02/07/05
Project Management Plan
Version 2.0
1.1.4 Schedule
Schedule Summary
The project schedule shown below incorporates the project phases, major milestones,
key deliverables and planned delivery dates.
Contingency plans have been developed to mitigate risks associated with deliverables,
and those contingencies are included in the table in Section 4.1, Risk Management
Assessment.
Planned Delivery
Date
WBS
Task Name
1
Project Management
06/24/05
1.1
Project approval from Class Managers (milestone)
11/05/05
1.2
Project Planning
01/26/05
Deliverable: Project Schedule
01/18/05
Deliverable: Project Charter
01/05/05
01/18/05
Deliverable: Project Management Plan
Communication Plan
01/18/05
1.3
Project Monitoring & Control
06/24/05
2
Analysis & Design
02/14/05
2.1
Develop Training Curriculum Approach
01/31/05
Deliverable: Training Curriculum Methodology
01/31/05
2.2
Develop Survey Approach for State
01/27/05
Deliverable: Training Curriculum Methodology
01/27/05
Page 12 of 47