Application And Permit For Dust Abatement Of County Roads Form - Teton County Road And Bridge Department Page 2

ADVERTISEMENT

Permit No.______________________
General Requirements
Signed and dated
1.
Completed Application:
payable by cash or check)
2.
Application Fee (Contractor): $30 (
Instructions for the Applicant/Contractor
No work shall be started until an authorized representative of the Teton County has given written notice to the Applicant to proceed,
except in case of an emergency when verbal authorization may be given with a written permit within five (5) working days.
Clearly mark the limits of the intended treatments so the inspector can make an accurate evaluation of the road condition. The area to
receive dust abatement will be marked at the (4) corners of the project with whiskers. Please allow (5) business days for completion of the
evaluation.
Notify the Teton County Road & Bridge Dept. (208) 354-2932 within 24 hours after the treatment was applied.
Upon completion of the treatment, the County will NOT grade the treated portion of the road as long as the road remains in good
conditions provided the whiskers installed are clearly visible to the grader operator. However, if in the County’s opinion the condition of the
road deteriorates so that it is no longer safe or comfortable to drive, the County will grade the road as needed. You may or may not be
notified prior to grading.
The County may impose other requirements and restrictions as required and is at the sole discretion of the Teton County Public Works
Director.
The application of diesel fuel, stove oil, motor oil, etc. for dust abatement purposes is STRICTLY PROHIBITED by law.
Applicant/Contractor is liable for any accidents of incidents that arise from the road treatment.
In accepting this permit, the Applicant, its successors and assigns, agrees to hold the Teton County harmless from any liability caused
by the application of dust abatement.
Neither the acceptance of this permit nor anything herein contained shall be construed as a waiver by the Applicant or any rights given
it by the constitution or laws of the State of Idaho or of the United States.
If the applicant/contractor does not comply with the conditions of this permit, no additional permits will be issued to the contractor.
Dust abatement treatments are only effective during the dry season. The treated portion of the road will be included in the regular
gravel road maintenance schedule as soon as the rainy season resumes.
(Initial)________
Permit Issuance Checklist
1.
County reviews application, in the order it was received. Additional information from the applicant may be needed.
2.
County inspects the road to determine if any maintenance is needed prior to the abatement.
3.
If maintenance is needed, staff will attempt to schedule the work at least (1) week prior to the scheduled application of dust
abatement material.
4.
County prepares permit, develops conditions & special provisions (typically within (10) business days of receiving a complete
application packet).
Contractor
Contractor
Signature
Printed Name
Date
_____________________________________
_________________________________________
___________
Applicant
Applicant
Signature
Printed Name
Date
_____________________________________
_________________________________________
___________
For Office Use Only
Rec’d By: ___________________________ Date: _______________________ Permit #: __________________________
Approved __ By: _________________________ Date: _______________________
Permit Fee $30 Cash ___________ Check# ___________ Rec’d By: ____________ Date: _____________
Page 2 of 2

ADVERTISEMENT

00 votes

Related Articles

Related forms

Related Categories

Parent category: Legal
Go
Page of 2