1.3 Existing Site Conditions
Describe the existing site conditions, including the storm drainage system. Include quantities of flow and site
conditions around all points of surface water discharge from the site.
1.3 Sequence of Major Construction Activities
Describe the intended sequence and timing of activities that disturb soil on the site. Include the following:
•
Clearing and grubbing for areas necessary for installation of perimeter erosion control devices
•
Construction of perimeter erosion control devices
•
Remaining interior site clearing and grubbing
•
Installation of permanent and temporary stabilization measures
•
Road grading
•
Grading for the remainder of the site
•
Utility installation and whether storm drains will be used or blocked after construction
•
Building, parking lot, and site construction
•
Final grading, landscaping, or stabilization
•
Implementation and maintenance of final erosion control structures
•
Removal of temporary erosion control devices