Project Implementation Plan Page 13

ADVERTISEMENT

Page 13 of 20
FM0027-GDL-00034-E-V15
If the cell is highlighted
in red
then the source of co-financing in relation to the awarded grant rate is
not in compliance with the Guide on Co-Financing Ceilings.
[5.5]
Percentage of total eligible expenses to be disbursed on approval of Project Completion
Report (PCR)
The percentage set in the Grant Agreement.
[5.6]
Advance offset mechanism
The mechanism defined in the Grant Agreement. This can take one of five values:
1. The whole advance is set off against the first payment claim
2. The advance is set off in equal proportions from the first payment claim until 80% of the
grant has been spent
3. The whole advance is set off when 80% of the grant has been spent
4. Manual advance offset scheduling
5. Not Applicable
In the first three of these, the PIP calculates the offset for the advance, and adjusts the planned
disbursement accordingly. The fourth enables a custom offset schedule to be entered, and the fifth is
used if no advance payment is planned.
[5.7]
PIR number
The PIP provides space for the maximum possible number of PIRs that could be submitted on the
project, based on the minimum reporting period duration of three months. If the planned project
duration is not a multiple of three months, then at least one period will need to be longer than three
months.
It is not mandatory to use the maximum number of PIRs – the PIP enables reporting period durations
of up to one year to be selected.
[5.8]
Reporting period start month
The start month of the period on which a PIR reports. The start month of PIR #1 is always the planned
start date of the project. The start month of PIR #<n+1> is always the month following the end month
of PIR #<n
>.
[5.9]
Reporting period end month
The end month of the period on which a PIR reports. This is selected from a drop-down list, with the
shortest reporting period being three months, and the longest being one year. If the end of the project
falls within one year, then there may be empty spaces at the bottom of the list – the user will need to
use the drop-down scroll bars to access the top of the list.
[5.10]
Likely disbursement month
The month in which the FMO is likely to disburse funds claimed in this PIR. This is set to three months
after the end of the reporting period, and assumes that the Promoter will submit the PIR to the Focal
Point at the beginning of the month following the end of the reporting period. The date calculated in
this field assumes that the information in the PIR is of a high enough quality to enable timely
evaluation of the payment claim – if this is not the case the disbursement date is likely to be delayed.
[5.11]
Advance offset
The amount of the advance to be offset in a reporting period. This includes both the offset against the
Financial Mechanism(s) grant, and the cash co-financing.
This row is read-only, and the data is calculated by the PIP for all offset mechanisms other than
‘Manual advance offset scheduling’, in which case the user can enter the amounts to be offset in each
reporting period.
[5.12]
Disbursement
The amount that the Financial Mechanism(s) plan to disburse in a given reporting period.
Financial Mechanism Office, 12/16, Rue Joseph II, 1000 Brussels, Belgium . Tel: +32 (0)2 286 1701 . Fax: +32 (0)2 286 1789 . Email: fmo@efta.int .

ADVERTISEMENT

00 votes

Related Articles

Related forms

Related Categories

Parent category: Business