Project Implementation Plan Page 14

ADVERTISEMENT

Page 14 of 20
FM0027-GDL-00034-E-V15
[5.13]
Cash co-financing from central, regional or local government budget
The co-finance that must be made available in a given period from government sources.
[5.14]
Cash co-financing from non-government sources
The co-finance that must be made available in a given period from non-government sources.
[5.15]
Disbursement to date
The planned cumulative funding of the project by the Financial Mechanism(s) from the start of the
project to date.
[5.16]
Cash co-financing to date
The planned cumulative funding of the project by government and non-government sources of cash co-
finance from the start of the project to date.
[5.17]
In-kind contribution to date
The planned cumulative value of in-kind contributions from the start of the project to date.
[5.18]
Total funding to date
The planned total funding of eligible expenses from the start of the project to date (the total of [5.15],
[5.16] and [5.17].
3.6 Part VI: Project Revenue
This section is identical to the ‘Revenues associated with the project’ section of the Application form –
details of how to complete this can be found in the appropriate version of the ‘Application form User
Guide’, available on
Financial Mechanism Office, 12/16, Rue Joseph II, 1000 Brussels, Belgium . Tel: +32 (0)2 286 1701 . Fax: +32 (0)2 286 1789 . Email: fmo@efta.int .