Material Requirements Planning
PART 11 (gross requirements given)
net requirements?
Planned order release?
Net requ.(week 2) = 600 – (1600 + 700) = -1700 =>Net requ.(week2) = 0
Net requ.(week 3) = 1000 – (1700 + 200) = -900 =>Net requ.(week3) = 0
Net requ.(week 4) = 1000 – 900 = 100 etc.
week
current
1
2
3
4
5
6
7
8
gross
requirements
600
1000
1000
2000
2000
2000
2000
scheduled
receipts
400
700
200
projected
inventory
balance
1200
1600
1700
900
0
0
0
0
0
net
requirements
100
2000
2000
2000
2000
planned receipts
planned order
release
Production Management