Material Requirements Planning
Assumptions:
lot size: 3000
lead time: 2 weeks
week
current
1
2
3
4
5
6
7
8
gross
requirements
600
1000
1000
2000
2000
2000
2000
scheduled
receipts
400
700
200
projected inventory
balance
1200
1600
1700
900
2900
900
1900
2900
900
net requirements
100
2000
2000
2000
2000
planned receipts
3000
3000
3000
planned order
release
3000
3000
3000