however, this time frame may not be sufficient.
Contacts with personnel at
plants with these units indicate that -more than 180 days may be needed
for equipment shakedown.
This is due to their complexity and the increased
number of interlocks on each phase of production that will shut the entire
plant down, should an upset occur.
These personnel indicated that up to 1
year may be needed to reach normal operation.
18